The Symbios Logic Fabrication #3 project is the quintessential high-tech facility.
The project included the construction of a 5” chip wafer fabrication facility, along with a new central plant to support Symbios Logic’s Colorado Springs Fabrication Facility. Cobb Mechanical Contractors worked in a design-build partnership with ADPMarshall and remained on the project through clean room tool installation and fit-up.
Location: Colorado Springs, Colorado
General Contractor: ADP Marshall
Mechanical Contract Value: $5,810,000
Date Completed: 1995
General Contractor: ADP Marshall
Mechanical Contract Value: $5,810,000